Boerne High School Renovations

Show on Homepage: 
No

Challenge

Improve drainage, preserve trees, demolish, alter and add buildings, increase parking capacity to the existing high school campus and complete construction in 12 months for the Boerne Independent School District (BISD).

 

Solution

The Coyle team worked with the project architects and BISD Bond Administrator to design proposed improvements to meet the goals and objectives of the bond.

 

Services Provided

Coyle Engineering prepared construction documents for new restrooms, additional bleachers and sidewalks for the football stadium, as well as all site improvements in the redesigned campus including parking lots and driving lanes, drainage improvements, ADA compliant sidewalks, ramps and stairs, utility connections and fire protection improvements.